Which of these is NOT correct about project management?
Options
A It has a beginning and an end
B Every project serves the government
Correct Answer
C It outputs through the process of implementation
D Project management requires additional management
Correct Answer

Option B is the correct answer.

Detailed Explanation

Projects serve various entities including private corporations and non-profits, not exclusively the government[cite: 4].

Hint

Consider which option makes an overly broad, restrictive assumption about project ownership.