One distinguishing factor of Critical Path Method is that it is:
Correct Answer
Option D is the correct answer.
Detailed Explanation
CPM uses single, fixed duration estimates (deterministic), whereas PERT uses probabilistic 3-point estimates[cite: 4, 5].
Hint
CPM assumes single known task durations.