AMS 104 Past Questions AMS 104 5 Objective Question

Question

One distinguishing factor of Critical Path Method is that it is:
Options
A Probabilistic
B Monotone
C Critical
D Deterministic
Correct Answer
Correct Answer

Option D is the correct answer.

Detailed Explanation

CPM uses single, fixed duration estimates (deterministic), whereas PERT uses probabilistic 3-point estimates[cite: 4, 5].

Hint

CPM assumes single known task durations.