The difference between the earliest starting time and the latest starting time for all activities on the critical path is:
Correct Answer
Option C is the correct answer.
Detailed Explanation
Activities on the critical path have zero float/slack, meaning Earliest Start Time equals Latest Start Time ($LS - ES = 0$)[cite: 4, 5].
Hint
Critical path activities have zero float.