The difference between the earliest starting time and the latest starting time for all activities on the critical path is:
Options
A > 0
B < 0
C = 0
Correct Answer
D ≥ 0
Correct Answer

Option C is the correct answer.

Detailed Explanation

Activities on the critical path have zero float/slack, meaning Earliest Start Time equals Latest Start Time ($LS - ES = 0$)[cite: 4, 5].

Hint

Critical path activities have zero float.