Question Detail

AMS 104 Past Questions AMS 104 5 Objective Question

Question

For the critical path of the application, a project must satisfy which one of the following conditions: (1) the path must have a defined starting point alone (2) the jobs must have a defined ending point where (3) the path must be continuous (4) calculated from the earliest starting time:
Options
A (1) & (2)
B (2) & (3)
Correct Answer
C (3) & (4)
D (1), (2) & (3)
Correct Answer

Option B is the correct answer.

Detailed Explanation

Network path criteria require defined start/end points and continuous dependency connections throughout[cite: 4].

Hint

Check the requirements for network completeness and path continuity.

Question Info