Question Detail
Question
For the critical path of the application, a project must satisfy which one of the following conditions: (1) the path must have a defined starting point alone (2) the jobs must have a defined ending point where (3) the path must be continuous (4) calculated from the earliest starting time:
Correct Answer
Option B is the correct answer.
Detailed Explanation
Network path criteria require defined start/end points and continuous dependency connections throughout[cite: 4].
Hint
Check the requirements for network completeness and path continuity.