The available time allowed to delay not to the completion time of such task in the network path is:
Options
A Total Float
B Free Float
Correct Answer
C Independent Float
D Available Float
Correct Answer

Option B is the correct answer.

Detailed Explanation

Free float is the time an activity can be delayed without delaying the early start of any successor[cite: 4].

Hint

Float that doesn't delay subsequent successor activities.