The project life cycle consists of:
Options
A Initiation, Planning, Execution, Monitoring, Closure
Correct Answer
B Hiring, Training, Production, Marketing
C Purchasing, Installation, Maintenance, Disposal
D Design, Prototyping, Testing, Launch
Correct Answer

Option A is the correct answer.

Detailed Explanation

These five phases form the standard structure of a project's lifecycle[cite: 5].

Hint

Select the standard 5 project phase process group sequence.