Question Detail

AMS 104 Past Questions AMS 104 5 Objective Question

Question

Which phase involves defining project objectives and scope?
Options
A Initiation
Correct Answer
B Execution
C Monitoring
D Closure
Correct Answer

Option A is the correct answer.

Detailed Explanation

The initiation phase defines the purpose, scope, and goals of the project[cite: 5].

Hint

The phase where goals and scope statement are first defined.

Question Info