Question Detail

AMS 104 Past Questions AMS 104 5 Objective Question

Question

Risk management plans are developed in:
Options
A Planning
Correct Answer
B Initiation
C Closure
D Execution
Correct Answer

Option A is the correct answer.

Detailed Explanation

Risks are identified, analyzed, and mitigation strategies are created during planning[cite: 5].

Hint

Anticipating issues and preparing mitigation plans before execution.