Question

A project charter is created during:
Options
A Initiation
Correct Answer
B Execution
C Monitoring
D Closure
Correct Answer

Option A is the correct answer.

Detailed Explanation

The project charter authorizes the project and is written in the initiation phase[cite: 5].

Hint

The document authorizing project start.